Manje Erie Studio Drone (10th Street)

Stained Glass will be removed soon. Dale looks B.A.

That steel will not support the data center. The entire floor of the future data center will be cut out and replaced.

Looks pretty sketch here, but not for long.

Framing for offices, staging area, restrooms are on the right. Voice team area is located in area by the windows. Immediate left is the data center.

Early shot of the fourth floor before framing began. North windows and facade have been removed.

IT floor.

2nd Floor

On the immediate right are the restrooms. Each floor has an identical set of male and female restrooms.

South Side

This is the future home of a stair way that goes from 1-4.

Super strong floor framing with new i-beams underneath will eventually have concrete poured on top.

Horizontal pieces attached to the studs are specially designed to minimize vibration to help deaden the sounds through the offices. The fronts of the offices will be glass.

Another view up through the floors.